MIAX Options Exchange - Updated target dates and parallel duration period for planned network refresh for the 10G ULL Extranet
As previously announced in the November 7, 2024 Alert, MIAX Options will upgrade the 10G ULL extranet switches and related network analytics infrastructure beginning in March 2025.
This updated alert supersedes previously communicated target dates and parallel duration period.
The 10G ULL Extranet upgrade is intended to improve the network’s latency performance and precision of the analytics infrastructure’s timestamp measurements.
The upgraded MIAX Options Extranet will be available in parallel with the existing MIAX Options Extranet from March 31, 2025 through April 11, 2025. All firms with 10G ULL Cross Connects (CCs) must establish and migrate their CC usage to the upgraded MIAX Options Extranet by April 11, 2025.
The transition plan for migration to the upgraded MIAX Options Extranet includes the following:
Please contact MIAX Trading Operations at TradingOperations@miaxglobal.com or (609) 897-7302 to arrange testing or to receive additional information on the planned network refresh.
This updated alert supersedes previously communicated target dates and parallel duration period.
The 10G ULL Extranet upgrade is intended to improve the network’s latency performance and precision of the analytics infrastructure’s timestamp measurements.
The upgraded MIAX Options Extranet will be available in parallel with the existing MIAX Options Extranet from March 31, 2025 through April 11, 2025. All firms with 10G ULL Cross Connects (CCs) must establish and migrate their CC usage to the upgraded MIAX Options Extranet by April 11, 2025.
The transition plan for migration to the upgraded MIAX Options Extranet includes the following:
- MIAX Options will coordinate with firms to establish new CCs on the upgraded MIAX Options Extranet.
- LOAs for new CCs will be available beginning January 6, 2025.
- Firms are required to request LOAs at least 4 weeks prior to their planned cutover date, which falls within the March 31, 2025 to April 11, 2025 (previously April 30, 2025) parallel period.
- Firms are required to complete all LOA requests no later than March 14, 2025 to ensure new CCs are established prior to April 11, 2025 (previously April 30, 2025).
- Requests for new CCs on the upgraded MIAX Options Extranet will be limited to one-for-one replacements of existing CCs.
- Firms may migrate existing transit and source IP subnets to the new CCs or can request new subnets.
- New CCs will meet the MIAX Options optical length specifications.
- New 10G ULL Extranet mandatory testing
- Firms targeting migration to the upgraded MIAX Options Extranet on March 31, 2025, its first day of availability, must participate in mandatory testing on Saturday March 29, 2025 from 9:00 am to 12:00 pm ET.
- Firms targeting utilization of the upgraded MIAX Options Extranet after March 31, 2025 are required to contact TradingOperations@MiaxGlobal.com to coordinate the transition to the upgraded MIAX Options Extranet.
- Firms are required to perform the following when transitioning to the upgraded MIAX Options Extranet:
- Verify all 10G ULL CC by logging into each subscribed application for each CC (i.e. establish application level socket connections to MEO, MEI, FOI, CTD, etc., for all ports, across all intended CCs) and verify the login.
- Confirm heartbeat receipt for both the A & B market data feeds for all subscribed multicast feeds across each intended firm CC.
- After verifying connectivity, firms must send an email to TradingOperations@miaxglobal.com and receive confirmation that testing was completed.
- Existing 1G LL Extranet and legacy remaining 10G ULL Extranet CCs optional testing
- There are no changes to the 1G LL switches on the firm side. However, MIAX Options will need to make internal configuration updates and firms with 1G LL connectivity are strongly recommended to participate in the above described testing on Saturday, March 29, 2025.
- There are no changes to the legacy 10G CCs on existing 10G ULL Extranet switches. However, MIAX Options will need to make internal configuration updates and firms with 10G ULL connectivity on the existing 10G ULL Extranet are strongly recommended to participate in the above described testing on Saturday, March 29, 2025.